WCPGW - PROGRESS PAYMENTS BY STAGE

5 January 2015

 

Most of the time, the construction of an architect-designed project proceeds according to plan. Construction unfolds on time. The construction documentation is clear and free of ambiguity. The trades perform their work skilfully and conscientiously. There are few surprises, be they physical or financial. The builder, owner and architect maintain a positive working relationship.

Sometimes though, construction does not proceed according to plan. Through negligence, disagreement or accident, a project is derailed. The derailment might last a moment in time, soon forgotten, or it might endure the entire project, poisoning both the process and relationships.

We have experienced and survived a number of derailments. They are stressful, sometimes expensive and always fractious. They test the good intentions of everyone involved.

What follows is the 2nd of eight disaster lessons from site. We ask what went wrong and review what we’ve changed in our practices to prevent it from happening again. An archive of the series can be accessed here.

2. Progress payments by stage

 

What happened

It is typical for a builder to claim payments for his work on a monthly basis, where the sum claimed corresponds to the value of the work undertaken in the past month. The builder instead requested that payments be made by stage. This involves regulated percentages that can be claimed at the completion of stipulated stages of construction:

Base stage – 10%
Framing stage – 15%
Lock-up stage – 35%
Fixing stage – 20%
Completion – 20%

Staged payments are larger but less regular than monthly payments. We recognised that this request likely related to the builder’s aversion to paperwork, but were unable to see any problem with it, so accepted his request.

What happened next

After the first few months of construction had passed, it became clear that the staged payments were a problem for the builder. They were simply spread too far apart. He might not have liked the paperwork involved with monthly payments, but the stop-start cashflow really hurt him.

This had two important effects:

First, he began to disappear from site for weeks at a time. Though the builder refused to provide explanations for his absences, we suspected he was taking on smaller commissions with fast turnarounds to keep the money flowing. These periods of non-activity on site stacked alarmingly, stretching what was supposed to be a nine month construction period out to 18 months.

Second, in order to reduce the money he would owe subcontractors, he began to take on specialist trades like concreting, plastering, plumbing and hydronic heating himself. He had to redo many of these, as his workmanship was not up to an acceptable standard. He also made errors that were impossible to rectify, things like bootprints in finished concrete surfaces and hydronic heating lines emerging crookedly from concrete slabs.

Why we think it happened

Though the builder never came clean with us or our client, we had no doubt that he was struggling financially. If the project had proceeded according to schedule, he would have received his staged payments once every two months or so. As the schedule stretched further and further, there were times when four or five months passed without payment. The poor cashflow created a vicious cycle that stretched the project timeline and impeded cashflow further.

The builder was not capable of extricating himself from this cycle. He had dug his own hole and everything he did, in terms of both his poor scheduling and inattention to quality, only served to make the hole deeper.

The lesson we learnt

This experience was powerful proof of the importance of cashflow on site. Consider: on a $500,000 project, the builder’s profit margin is around 15%. In other words, he pays and receives $425,000 in order to earn just $75,000. He also has to pay suppliers and subcontractors before our client pays him, the gap between which might be as much as two months. He must therefore keep the money coming in or the cycle will disintegrate.

The lesson we learnt was simple: we no longer accept project payments by stage. Even if the builder is paperwork-shy, and we must produce additional paperwork to compensate, we insist on monthly payments.

 

Warwick Mihaly Director – Insurance & Member Services
This article appeared in Warwick’s blog Panfilo in December 2014 as part of a series of articles on disaster lessons from site: https://panfilo.co/tag/disaster-lessons-from-site/

Disclaimer – ‘What could possibly go wrong?’ is not an advice column, it is only general comment from ArchiTeam who are not aware of your circumstances with any issue that you may have. You cannot rely on these general comments, each member must make their own decisions about any action they should take and seek independent advice of their own if they are unsure.